West Midlands Police Central Traffic Unit Car Park

£246,000

The scheme involved the reconstruction and resurfacing of the main car park for the West Midlands Police at the Central Traffic Complex at Aston.

To maintain programme and continuity of work details of all daily deliveries were provided to on-site security personnel to enable them to monitor all site movements and minimise the potential of encroachment by unexpected visitors.

One of the challenges associated with the works was working in a “live” environment. This involved extensive liaison with the Complex Fleet Manager to enable us to phase the works and minimise disruption to the operation of the facility. The works were undertaken in four distinct phases enabling access to be maintained with minimum hindrance to the works programme.